Great progress and great photos from Hutton Construction at the new JCHS campus!
Some of the restrooms are complete enough for tile work to commence.

Drywall has been put up in the upstairs are where the future academy offices and biology and chemistry labs will be.

Concrete has been poured and block walls are up in the child development, ceramics, and art rooms.

Concrete floor is in and steel is going up in the new commons area, between the kitchen and the main gym.

The auxiliary gym floor has been poured and crews are preparing to install the tilt-up wall panels.

The floor to the football concessions building is poured and ready for walls to start going up.